Resources

Client Alerts, News Articles, Blog Posts, & Multimedia

Everything you need to know about BMD and the industry.

CLIENT ALERT: Construction Law Update: Communication is Key! And Other Lessons Learned From A Recent Public Project Court Decision

Client Alert

In a recent decision, the Ohio Court of Claims entered a $2.2 million judgment in favor of the general trades contractor, and against a public university, in connection with an on-campus renovation project. Mid American Construction, LLC v. Univ. of Akron, Ct. of Cl. No. 2016-00685JD, 2018-Ohio-4513.

Delivered as a “multi-prime” project, the university entered into separate contracts with a construction manager and an architect, in addition to separate contracts with the general trades, plumbing, HVAC, and electrical contractors. The project was delayed and the general trades contractor and university asserted breach of contract claims against one another, each arguing that the other party’s delays and failure to perform caused the other to suffer damages.

Following trial, Judge Crawford entered a decision finding that the university’s ongoing failure to pay for work, as well as problems with coordination and schedule, not only justified the contractor’s decision to walk-off the job, but also prevented the contractor from completing its work. Thus, the university was found liable to the general trades contractor in the amount of $2.2 million, while the university’s counterclaim was denied.

The Court’s detailed thirty-three (33) page decision offers many rules and reminders for public owners, contractors, construction managers, construction claims consultants, and damages experts alike:

1.  Communication is Key. In observing the risk inherent in all construction projects, Judge Crawford aptly noted: “[p]ublic construction contracts are vast documents containing thousands of construction and procedural details, all of which amount to legal promises, and some of which would be difficult to perform. Business at the construction site is performed by skilled and unskilled workers who seek to coordinate a schedule that is often developed at a laboratory away from the work site and without communication with those individuals putting one brick on top of another.”

The point is clear. Communication delivers results. The more communicative, transparent and effective the construction team functions, the better the results. In his opinion, Judge Crawford identified thirty (30) separate reasons for delays on construction projects, the majority of which arise in the pre-construction phase and can easily be avoided with more effective communication.

What are you doing to improve communication, both internally and with other project participants? 

2.  Control What You Can Control. This decision also serves as a reminder to project owners of the importance of selecting an appropriate project delivery method, taking steps to ensure that the design is adequately developed, considering input from all stakeholders, issuing payment in a timely manner, issuing timely approvals, delivering the site to the contractor in a timely manner, hiring qualified design and construction teams, and following the contract’s written notice requirements.

Likewise, it is incumbent on contractors to identify and provide notice of unrealistic schedules, errors in contract documents, apparent design errors, constructability concerns, and questions concerning scope. Contractors are also reminded that so long as they make an honest effort to perform their contracts, and do not willfully refuse to perform, they are entitled to some portion of the contract price so long as they achieve substantial completion.

3.  The Value (or Cost) of a Good (or Bad) Construction Manager. This decision is a cautionary tale for owners and construction managers alike as the university’s liability arose, in part, from the failings of its construction manager. If the owner chooses to implement the Construction Manager At-Risk project delivery method, it must carefully select a qualified construction manager. Equally important, construction managers must deliver value to the project and their owner clients by following contract requirements such as conducting partnering sessions with contractors, providing monthly progress reports, providing look-ahead schedules, maintaining accurate and current schedule updates, timely responding to RFI’s and executing CCDs, and appropriately coordinating among contractors.

4.  Credibility Matters. If a claim arises that escalates to litigation or arbitration, judges and arbitrators tend to believe and find credibility with witnesses who are not evasive when asked tough questions, maintain a patient and frank demeanor, and provide consistent answers supported by the project documents.

5.  Battle of the Experts. Along the same lines, if a claim arises that requires expert testimony, judges and arbitrators have a tendency to agree with experts who are well-qualified, thorough, maintain an objective demeanor and deliver objective explanations, and offer testimony that is not conclusory, but is based on support and factual detail.

6.  Liquidated Damages or Compensatory Damages, But Not Both. Liquidated damages are not available under Ohio law where the party seeking to impose them is found to have contributed to an unreasonable delay. However, even in instances where a court may find a liquidated damages clause enforceable, and the party seeking damages is not in breach, it is well-settled law in Ohio that a non-breaching party may not recover both compensatory and liquidated damages.

For additional information, please feel free to contact Attorney Justin Alaburda at Brennan Manna & Diamond. He can be reached at www.jmalburda@bmdllc.com, or (330) 253-9134. 


Latest Batch of Ohio Chemical Dependency Professionals Board Rules: What Providers Should Know

The Ohio Chemical Dependency Professionals Board recently released several new rules and proposed amendments to existing rules over the past few months. A hearing for the new rules was held on February 16, 2024, but the Board has not yet finalized them.

Now in Effect: DOL Final Rule on Classification of Independent Contractors

Effective March 11, 2024, the U.S. Department of Labor (DOL) has adopted a new standard for the classification of employees versus independent contractors — a much anticipated update since the DOL issued its Final Rule on January 9, 2024, as previously discussed by BMD.  In brief, the Fair Labor Standards Act (FLSA) creates significant protections for workers related to minimum wage, overtime pay, and record-keeping requirements. That said, such protection only exists for employees. This can incentivize entities to classify workers as independent contractors; however, misclassification is risky and can be costly.

Florida's Recent Ruling on Arbitration Clauses

Florida’s recent ruling on arbitration clauses provides a crucial distinction in determining whether such clauses are void as against public policy and providers may have the opportunity to include arbitration clauses in their patient consent forms. On March 6, 2024, Florida’s Fourth District Court of Appeals reversed and remanded Florida’s Fifteenth Circuit Court ruling of Piero Palacios v. Sharnice Lawson. The Court of Appeals ruled that the parties’ arbitration agreement did not contradict the Legislature’s intent of Florida’s Medical Malpractice Act (the “MMA”), but rather reflects the parties’ choice to arbitrate claims entirely outside of the MMA’s framework. Therefore, the Court found that the agreement was not void as against public policy.

Corporate Transparency Act Update 3/14/24

On March 1, 2024, a federal district court in the Northern District of Alabama concluded that the Corporate Transparency Act (“CTA”) exceeded Congressional powers and enjoined the Department of the Treasury from enforcing the CTA against the plaintiffs. National Small Business United v. Yellen, No. 5:22-cv-01448 (N.D. Ala.). On March 11, 2024, the U.S. Department of Justice appealed the district court’s decision to the Eleventh Circuit Court of Appeals.

The Ohio State University Launches Its Accelerated Bachelor of Science in Nursing Program

In response to Ohio’s nursing shortage, The Ohio State University College of Nursing is accepting applications for its new Accelerated Bachelor of Science in Nursing program (aBSN). Created for students with a bachelor’s degree in non-nursing fields, the aBSN allows such students to obtain their nursing degree within 18 months. All aBSN students will participate in high-quality coursework and gain valuable clinical experience. Upon completion of the program, graduates will be eligible to take the State Board, National Council of Licensure Exam for Registered Nursing (NCLEX-RN).